UPGRADING OF EXISTING EAST, WEST
AND NORTH WHARVES AT PASIR GUDANG

A 250m length of existing wharf needed to be upgraded to meet the higher loading capacity of an oil rig jacket. Sime Darby Engineering Sdn Bhd appointed HSS to provide the specialist engineering inputs for the project through to implementation. HSS was responsible for feasibility studies, detailed engineering design and preparation of structural detail drawings, tender documentation and supervision of construction.

01

Client

Sime Darby Engineering

03

Duration

2010 — 2012

02

Our Service

Engineering Design

04

Location

Johor, Malaysia

Scope Of Work

Feasibility study, detail design and preparation of structural detail drawings, tender documentation and site supervision.