SULTANAH AMINAH HOSPITAL - REHABILITATION
This assignment carried out in association with Taywood Engineering Ltd, required the dimensional and condition survey of the building, involving reinforcement assessment using covermeter instruments and selective concrete breakouts to determine reinforcement configuration. Recommendations for repair methods included cathodic protection and implementation of inspection and maintenance programme.
Client
Jabatan Kerja Raya
(JKR)
Duration
1988 — 1994
Our Service
Engineering Design & Construction Supervision
Location
Johor, Malaysia
Scope Of Work
Dimensional and condition survey
Design analysis and overall assessment of structural integrity
Implementation of a complete inspection and maintenance programme
Construction Supervision