NAD AL SHABA RACE COURSE, AND MIXED USE DISTRICTS, DUBAI

This project involved the development of 365ha of mixed-use district. It needed the upgrading of the existing racecourse, Nad Al Shaba Racecourse, comprising of additional stables, track configuration and grandstand. HSS produced more than 3500 drawings and had to complete the designs of all infrastructure within 6 months. HSS provided detailed design and supervision of construction for the infrastructure works and utility requirement for the development. This assignment was won on an international bid competing with some of the big international firms from US and Europe.

01

Client

TAK Design Consultants

03

Duration

2006 — 2007

02

Our Service

Engineering Design

04

Location

United Arab Emirates

Scope Of Work

Professional Engineering Consultancy Services for the filling stages

Piping for District Cooling System

Concept design

Preliminary design

Detail design

Tender stages

Picture1
× How can I help you?